Start Date
|
End Date
|
Title
|
Location
|
Type of Work
|
Impact
|
SPW
|
|
3/9/2026
|
3/13/2026
|
CP2 Monument to Crossover Pigging
|
Pipe - Panola
|
Pigging
|
1
|
|
|
3/17/2026
|
3/20/2026
|
Panola 1 &2 Spring Compressor Maintenance
|
Panola Compressor
|
Annual Maintenance
|
8
|
61648
|
|
3/23/2026
|
3/24/2026
|
Pigging Line CP
|
Pipe - Panola
|
Cleaning Pig
|
1
|
|
|
3/24/2026
|
3/25/2026
|
Pigging Line Gulf Run CP, Panola to Westdale
|
Pipe - Panola
|
Cleaning Pig
|
1
|
|
|
3/24/2026
|
4/2/2026
|
Vernon Spring Compressor Maintenance
|
Vernon Compressor
|
Annual Maintenance
|
8
|
61691
|
|
4/7/2026
|
4/10/2026
|
Panola 3 Spring Compressor Maintenance
|
Panola Compressor
|
Annual Maintenance
|
8
|
62290
|
|
4/13/2026
|
4/17/2026
|
Alto Spring Compressor Maintenance
|
Alto Compressor
|
Annual Maintenance
|
8
|
61651
|
|
4/21/2026
|
4/21/2026
|
Golden Pass Outage
|
Golden Pass
|
Other
|
8
|
62325
|
|
4/21/2026
|
4/24/2026
|
Westdale Spring Compressor Maintenance
|
Westdale Compressor
|
Annual Maintenance
|
8
|
62324
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
1. No capacity impact is expected at
this time.
|
|
2. Coordinating with necessary loads.
|
|
3. Based on historical and current throughput, no capacity impact is expected. In the event
nominations increase significantly, restrictions may become necessary.
|
|
4. Coordinating maintenance with
interconnecting pipe to minimize customer
impact. No capacity impact is expected
at this time; however, if operating conditions change, affected parties will
be notified.
|
|
5. Affected production notified of
shut-in during work.
|
|
6. Customers may experience pressure
fluctuations, but no capacity impact is anticipated.
|
|
7. Based upon customer nominations,
restrictions may become necessary.
|
|
8. Based on all available information,
capacity will be impacted. Capacity
reductions will be done in accordance with the
provisions of GR's tariff regarding scheduling and interruption of services.
|