TW Planned Service Outage

Notice Type Description: Planned Service Outage
Notice Identifier: 90785
Critical Notice Description: Critical notice
Posting Date/Time: Sep 29 2022 3:27PM
Notice Status Description: Initiate
Required Response Indicator Description: No response required
Response Date/Time:
TSP: 7933047
TSP Name: TRANSWESTERN PIPELINE COMPANY, LLC
Subject: Station 4 (Klagetoh, AZ) - Unit 401 Engine overhaul. 11/1 thru 11/18/22
Notice Effective Date/Time: Nov 1 2022 9:00AM
Notice End Date/Time: Nov 11 2022 3:04PM

Notice Text:

Nominated Volume Affected

September 29, 2022


To: All Transwestern Pipeline Customers.

Subject: Thoreau Mainline West System Capacity.

Reason: Station 4 (Klagetoh, AZ) - Unit 401 Engine overhaul.

The capacity effects of this maintenance on the Thoreau Mainline West System are listed below.

Gas Day November 1st thru November 18th, 2022 (18 Days)

Thoreau Mainline West System capacity will be reduced from 1,240,000 MMBtu/d to approximately 1,100,000 MMBtu/d.

Based on expected scheduled volumes on the Mainline Thoreau West System, this maintenance may not impact any scheduled volumes during this timeframe.

Gas Day November 19th, 2022

Thoreau Mainline West System capacity will increase from 1,100,000 MMBtu/d to the original capacity of 1,240,000 MMBtu/d.


Transwestern reserves the right to revise the above listed schedule. Please ontinue to monitor Transwestern website for updates and scheduled changes.

Reason: Pipeline Maintenance
Location: Station 4 (Klagetoh, AZ)