TW Planned Service Outage

Notice Type Description: Planned Service Outage
Notice Identifier: 112978
Critical Notice Description: Critical notice
Posting Date/Time: Oct 20 2025 3:15PM
Notice Status Description: Initiate
Required Response Indicator Description: No response required
Response Date/Time:
TSP: 7933047
TSP Name: TRANSWESTERN PIPELINE COMPANY, LLC
Subject: Bloomfield Compressor Station - Unit 3 Turbine Engine exchange. 11/17 thru 11/21/25
Notice Effective Date/Time: Nov 17 2025 9:00AM
Notice End Date/Time: Nov 22 2025 8:59AM

Notice Text:

Nominated Volume Affected

October 20, 2025


To:
All Transwestern Pipeline Customers

Subject: Bloomfield Compressor Station - Located on the San Juan Lateral.

Reason: Unit 3 - Turbine Engine exchange.

Gas Day November 17th thru November 21st , 2025 (5 days)

Harvest Valverde capacity will be reduced from 230,000 MMBtu/d to zero.

Gas Day November 22nd, 2025

Harvest Valverde capacity will increase back up to the original capacity of 230,000 MMBtu/d.


Transwestern reserves the right to revise the abovelisted schedule. Please continue to monitor Transwestern website for updates and schedule changes.

Reason: Pipeline Maintenance
Location: Bloomfield Compressor Station - Located on the San Juan Lateral.