TW Planned Service Outage

Notice Type Description: Planned Service Outage
Notice Identifier: 112094
Critical Notice Description: Critical notice
Posting Date/Time: Sep 16 2025 11:15AM
Notice Status Description: Initiate
Required Response Indicator Description: No response required
Response Date/Time:
TSP: 7933047
TSP Name: TRANSWESTERN PIPELINE COMPANY, LLC
Subject: East Mainline System - Compressor Station maintenance. 9/23 thru 10/23/25
Notice Effective Date/Time: Sep 23 2025 9:00AM
Notice End Date/Time: Oct 24 2025 8:59AM

Notice Text:

Nominated Volume Affected

September 16, 2025


To: All Transwestern Customers

Subject: East Mainline system - Compressor Station maintenance.

Reason: Station 6 (Laguna, NM) & Station 7 (Mountainair, NM) - Engine & compressor maintenance.

This maintenance could affect receipt volumes from the West Texas & Panhandle Laterals flowing west through Station 9 (Roswell, NM).

Gas Day September 23rd thru October 13th, 2025

Total capacity for Station 9 receipt volumes (west flow) will be reduced from 750,000 MMBtu/d to approximately 650,000 MMBtu/d.

Gas Day October 14th thru October 16th, 2025

Total capacity for Station 9 receipt volumes (west flow) will be reduced from 650,000 MMBtu/d
to approximately 600,000 MMBtu/d.

Gas Day October 17th thru October 20th, 2025

Total capacity for Station 9 receipt volumes (west flow) will increase from 600,000 MMBtu/d to approximately 750,000 MMBtu/d.

Gas Day October 21st thru October 23rd , 2025

Total capacity for Station 9 receipt volumes (west flow) will be reduced from 750,000 MMBtu/d to approximately 600,000 MMBtu/d.

Gas Day October 24th, 2025

Total capacity for Station 9 receipt volumes (west flow) will increase from 600,000 MMBtu/d to approximately 750,000 MMBtu/d.


Transwestern reserves the right to revise the above listed schedule. Please continue to monitor Transwestern website for updates and schedule changes.

Reason: Pipeline Maintenance
Location: East Mainline System - Station 6 (Laguna, NM) & Station 7 (Mountainair, NM)