Updated as of
|
|
11/4/2024
|
|
|
|
|
Listed
below is a summary of the planned outages that could affect capacity or
impact any receipt/delivery locations during the PEPL 2024 outage season.?
This schedule is not a complete list of all outages and is subject to change
as the season progresses to reflect any project delays, cancellations or
additions.? Additionally, anticipated impact and restrictions are subject to
change.??
*All scheduled dates represent gas days as defined in the PEPL Tariff to mean
a period of twenty-four consecutive hours, beginning and ending at 9:00 a.m.
(Central Clock Time).
|
Start Date
|
End Date
|
Location
|
Unit(s)
|
Maintenance
|
Anticipated Impact
|
Meter(s) Impact
|
4/30/24
|
6/12/24
|
Pelham Road
|
Station
|
Rebuild
|
Meters will be shut in for
the duration of the outage.
|
02997-RIVER ROUGE PLANT
02513-DETROIT
|
5/1/24
|
5/20/24
|
Pelham Road
|
Station
|
Rebuild
|
Meter will be shut in for
the duration of the outage.
|
Location: UNION
|
5/2/24
|
5/10/24
|
Sooner
|
16"
|
Relay at Hwy 33 and HDD
|
Meters will be shut in for
the duration of the outage.
|
10632-DFS-KINGFISHER
41433-CHISOLM PLANT
41447-REEDING PLANT
41434-LINCOLN PLANT
|
5/2/24
|
5/10/24
|
Cashion
|
Station
|
Isolation ESD
|
Capacity through Cashion
Station may be limited.? Meter subject to scheduling reductions.
|
10632-DFS-KINGFISHER
|
5/9/24
|
5/17/24
|
Edgerton
|
100 Line
|
Anomaly Repair
|
All meters downstream of
MP 833.38 subject to scheduling reductions.
|
02654-IDA
02611-CARLETON
02997-RIVER ROUGE PLANT
05586-GUARDIAN GLASS
Location:UNION
Location:NATST
Location:MCON
|
5/28/24
|
5/28/24
|
West Line
|
100 Line
|
Tool Run
|
Meter will be shut in for
the duration of the outage.
|
09874-KALAMAZOO RIVER
GENERATION STATION/COMSTOCK
|
5/30/24
|
5/30/24
|
West Line
|
100 Line
|
Tool Run
|
Meter will be shut in for
the duration of the outage.
|
09874-KALAMAZOO RIVER
GENERATION STATION/COMSTOCK
|
6/4/24
|
6/4/24
|
West Line
|
100 Line
|
Tool Run
|
Meter will be shut in for
the duration of the outage.
|
09874-KALAMAZOO RIVER
GENERATION STATION/COMSTOCK
|
6/6/24
|
6/6/24
|
West Line
|
100 Line
|
Tool Run
|
Meter will be shut in for
the duration of the outage.
|
09874-KALAMAZOO RIVER
GENERATION STATION/COMSTOCK
|
6/6/24
|
6/21/24
|
Haven
|
200 Line
|
Coupling reinforcements
and valve replacements
|
Meter will be shut in for
the duration of the outage.
|
09225-GETTY GAS-BURNS
|
6/17/24
|
6/28/24
|
Fulton
|
Lateral
|
Pipe Replacement
|
Meter will be shut in for
the duration of the outage.
|
02085-HARBISON-WALKER-FULTON
|
6/18/24
|
6/18/24
|
DOGWOOD
|
Meter
|
Tie-In after Hydrotest
|
Meter will be shut in for
the duration of the outage.
|
09236-DOGWOOD
|
6/21/24
|
6/27/24
|
ONEOK GAS
|
Meter
|
Meter Upgrades
|
Meter will be shut in for
the duration of the outage.
|
09069-ONEOK GAS
TRANSPORTATION
|
7/8/24
|
7/30/24
|
Edgerton
|
100 Line
|
Anomaly Digs
|
Location will be subject
to scheduling reductions.
|
Location: MCON
|
7/9/24
|
7/9/24
|
Edgerton
|
200 Line
|
Hydrotest
|
Meter will be shut in for
the duration of the outage.
|
02853-RICHLAND POWER PLANT
|
7/10/24
|
7/10/24
|
Edgerton
|
200 Line
|
Hydrotest
|
Meter will be shut in for
the duration of the outage.
|
02781-ANR PIPELINE CO.DEL.
|
8/6/24
|
8/6/24
|
Edgerton
|
200 Line
|
Hydrotest
|
Meters will be shut in for
the duration of the outage.
|
02781-ANR PIPELINE CO.DEL.
02853-RICHLAND POWER PLANT
|
8/20/2024
|
8/26/2024
|
Nipsco Defiance-Crossroads
Delivery
|
M&R
|
Painting
|
Meter will be shut in for
the duration of the outage.
|
Location: CRSRD
|
9/10/2024
|
9/13/2024
|
West Line
|
100 Line
|
Immediate Anomaly Dig
|
Meters will be shut in for
the duration of the outage.
|
02551-KALAMAZOO
09874-KALAMAZOO RIVER GENERATION/COMSTOCK
|
10/1/24
|
10/16/24
|
Sunray
|
100 Line
|
Gate replacement
|
Meters will be shut in for
the duration of the outage.
|
12840-SEABOARD
FARMS-WITTAKER 1-6
40524-SUNRAY GAS PLANT
|
10/1/24
|
10/2/24
|
Northern
Natural-Greensburg
|
M&R
|
New RTU Installation
|
Meter will be shut in for
the duration of the outage.
|
Location: NNATL
|
10/10/24
|
10/15/24
|
Seiling
|
100 Line
|
Valve Replacement
|
Capacity through Elk City
and Seiling will be limited.? Meters will be shut in for the duration of the
outage.
|
41420-MCCLURE INTERCONNECT
40466-ENOGEX-BECKHAM-WIT.
41215-DELHI CARPENTER RECEIPT
12744-ENBRIDGE-BECKHAM COUNTY
12666-ARKLA/NORAM-CUSTER RECEIVED
13241-MARK WEST GAS RECEIPT
41413-ONEOK SMALLWOOD
06132-K.N. ALEDO CHECK PURCHASE
41393-NINE MILE PLANT
41180-TAYLOR PLANT
09069-ONEOK GAS TRANSPORTATION
Location: HEMPH
|
10/11/24
|
10/15/24
|
Seiling
|
100 Line
|
Pipe Replacement
|
Capacity through Elk City
and Seiling will be limited.? Meters will be shut in for the duration of the
outage.
|
41420-MCCLURE INTERCONNECT
40466-ENOGEX-BECKHAM-WIT.
41215-DELHI CARPENTER RECEIPT
12744-ENBRIDGE-BECKHAM COUNTY
12666-ARKLA/NORAM-CUSTER RECEIVED
13241-MARK WEST GAS RECEIPT
41413-ONEOK SMALLWOOD
06132-K.N. ALEDO CHECK PURCHASE
41393-NINE MILE PLANT
41180-TAYLOR PLANT
09069-ONEOK GAS TRANSPORTATION
02428-PHIL CIM PURCHASE #1
Location: HEMPH
41424-ROSE VALLEY PLANT
Location: WTANA
|
11/5/24
|
11/11/24
|
Hooker
|
16"
|
Replace receiving barrel
|
Meters will be shut in for the
duration of the outage.
|
41152-DORCHESTER HUGOTON-MOUSER
41296-MOBILE MOUSER-DEFS STRT
Location: BAKER
|